Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.)
Name of the Agency :                   P.R. Deptt. 
Sl.
No. 
Name of the Work  Name of the
Block & District 
Specify Budget to be
spent under (Plan/Non-Plan/OHSP/NRHM
Project Cost
(In Lakh)
Total Allotment
received (In Lakh)
Expenditure (Amount in Lakh) Physical Progres 
Progress reported till
last review meeting 
Progress
during this month 
Cumulative
progress 
Not started
or in progress or completed 
If in progress,
please indicate the stage or if not started, reasons or if completed, handed over or not 
1 Infrastructure
Development of CHC Raghunathpur 
Raghunathpur
Jagatsinghpur 
Non plan grant  5.33 5.33 70% NIL 70% stopped since 8 months   Not completed, new building
constructed upto slab casting,
finishing work not started  
2 Infrastructure
Development of CHC Tirtol
Tirtol
Jagatsinghpur 
Non plan grant  5.33 5.33 70% 5% 75% In progress New building slab casting completed, Door & window fittings in progress
3 Infrastructure
Development of Erasama UGPHC 
Erasama
Jagatsinghpur 
Non plan grant  5.33 5.33 100% -- 100% completed  Finishing work not taken up since six months due to shortage of funds & not handed over  
4 Improvement &
Renovation of Tarikunda PHC (N)
Raghunathpur
Jagatsinghpur 
Non plan grant  3.00 3.00 100% -- 100% completed  New building constructed
& not handed over
5 Improvement &
Renovation of Jaipur PHC (N)
Raghunathpur
Jagatsinghpur 
Non plan grant  3.00 3.00 NIL NIL NIL Not started
--
6 Renovation to
Krushnanandapur PHC (N)
Tirtol
Jagatsinghpur 
Non plan grant  3.00 3.00 50% NIL 50% stopped since
8 months 
New building construction completed upto roof level 
7 Jagannathpur PHC (N) Tirtol
Jagatsinghpur 
Non plan grant  3.00 3.00 70% NIL 70% stopped since
6 months 
New building constructed, slab casting done finishing work not started
8 Gorada PHC (N) Kujanga
Jagatsinghpur 
Non plan grant  3.00 3.00 70% NIL 70% In progress Extension of room constructed,
slab casting completed, finishing work in progress  
9 Rahama PHC (N) Kujanga
Jagatsinghpur 
Non plan grant  3.00 3.00 50% NIL 50% stopped since
8 months 
Extension of room constructed,
slab casting completed, finishing work not taken up   
10 Potanai PHC (N) Kujanga
Jagatsinghpur 
Non plan grant  3.00 3.00 100% -- 100% completed  New structure constructed,
completed & handed over
11 Potanai PHC (N)
Compound wall 
Kujanga
Jagatsinghpur 
Non plan grant  3.00 3.00 0 0 0 Not started  Estimate nor prepared &
submitted for countersign.
Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.)
Name of the Agency :                   P.R. Deptt. 
Sl.
No. 
Name of the Work  Name of the
Block & District 
Specify Budget to be
spent under (Plan/Non-Plan/OHSP/NRHM
Project Cost
(In Lakh)
Total Allotment
received (In Lakh)
Expenditure (Amount in Lakh) Physical Progres 
Progress reported till
last review meeting 
Progress
during this month 
Cumulative
progress 
Not started
or in progress or completed 
If in progress,
please indicate the stage or if not started, reasons or if completed, handed over or not 
12 Malahunka PHC (N) Kujanga
Jagatsinghpur 
Non plan grant  3.00 3.00 100% NIL 100% Completed  Construction of compound wall completed & handed over 
13 Renovation to Balichua
PHC (N)
Erasama
Jagatsinghpur 
Non plan grant  3.00 3.00 100% NIL 100% Completed  One extension room constructed, completed & handedover
14 Panchapali PHC (N) Erasama
Jagatsinghpur 
Non plan grant  5.00 5.00 100% NIL 100% Completed  Renovation work, tile, door & window fixing,plastring,colouring, painting & handed over  
15 Dihasahi PHC (N) Erasama
Jagatsinghpur 
Non plan grant  4.00 4.00 100% NIL 100% Completed  Renovation work, tile, door & window fixing,plastring,colouring, painting & handed over  
16 Malipur PHC (N) Erasama
Jagatsinghpur 
Non plan grant  3.00 3.00 Not started  -- NIL Not started
Not started 
17 Piteipur PHC (N) Jagatsinghpur
Jagatsinghpur 
Non plan grant  3.00 3.00 100% NIL 100% Completed  Renovation work, tile, door & window fixing,plastring,colouring, painting & handed over  
18 Kaduapada PHC (N)  Jagatsinghpur
Jagatsinghpur 
Non plan grant  3.00 3.00 100% NIL 100% Completed  One extension room constructed, completed & handedover
19 Adhanga PHC (N) Biridi
Jagatsinghpur 
Non plan grant  3.00 3.00 100% NIL 100% Completed  One room constructed, completed &
handedover  
20 Bagalpur PHC (N) Biridi
Jagatsinghpur 
Non plan grant  3.00 3.00 60% NIL 60% stopped since
8 months 
Renovation work such as grading,
plastering, colouring completed
partial compound wall executed
21 Borikina PHC (N) Balikuda
Jagatsinghpur 
Non plan grant  3.00 3.00 80% NIL 80% Stoped
since
2 months 
Extension of one room constructed, some finishing work is pending 
22 Osakana PHC (N) Balikuda
Jagatsinghpur 
Non plan grant  3.00 3.00 60% NIL 60% Stoped
since
6 months 
Constructed one new building, slab
casting completed, finishing work
is pending 
Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.)
Name of the Agency :                   P.R. Deptt. 
Sl.
No. 
Name of the Work  Name of the
Block & District 
Specify Budget to be
spent under (Plan/Non-Plan/OHSP/NRHM
Project Cost
(In Lakh)
Total Allotment
received (In Lakh)
Expenditure (Amount in Lakh) Physical Progres 
Progress reported till
last review meeting 
Progress
during this month 
Cumulative
progress 
Not started
or in progress or completed 
If in progress,
please indicate the stage or if not started, reasons or if completed, handed over or not 
23 Dasabatia PHC (N) Balikuda
Jagatsinghpur 
Non plan grant  3.00 3.00 60% NIL 60% Work stopped
since 6 months 
Constructed one new building, slab
casting completed, finishing work
is pending 
24 Machhagaon PHC (N) Balikuda
Jagatsinghpur 
Non plan grant  3.00 3.00 NIL NIL NIL Work not
started 
Reason not known
25 Osakana PHC (N) Balikuda
Jagatsinghpur 
Non plan grant  3.00 3.00 NIL NIL NIL Work not
started 
Reason not known
26 Alanahat PHC (N) Naugaon
Jagatsinghpur 
Non plan grant  3.00 3.00 90% NIL 90% Work stopped
since 6 months 
One new building constructed,
finishing work completed site
development pending 
27 Deriki PHC (N) Naugaon
Jagatsinghpur 
Non plan grant  3.00 3.00 90% NIL 90% Work stopped
since 6 months 
One new building constructed,
finishing work completed site
development pending 
28 Construction of
Sub-Centre building at
Gobardhanpur
Kujanga
Jagatsinghpur 
RCH - II (ZSS) 5.50 5.50 NIL NIL NIL Not started
Reason not known
29 Kanaguli Sub-Centre Erasama
Jagatsinghpur 
RCH - II (ZSS) 5.50 5.50 100% NIL 100% Completed  New building constructed
Not handedover 
30 Olara Sub-Centre Erasama
Jagatsinghpur 
RCH - II (ZSS) 5.50 5.50 100% NIL 100% Completed  New building constructed & 
handedover 
31 Mundalo Sub-Centre Jagatsinghpur
Jagatsinghpur 
RCH - II (ZSS) 6.10 6.10 100% NIL 100% Completed  New building constructed
Not handedover 
32 Repair of Sub-Centre building
24 Nos.
8 Blocks
Jagatsinghpur
TFC 24.00 24.00 90% -- 90% 20 Nos. renovation completed  20 Nos. renovation work completed & handedover handedover, 2 Nos. not takenup & 2 Nos. in progress
33 Construction of building
under cluster housing
scheme
Manijanga, Kujanga, Balikuda
Jagatsinghpur 
Cluster Housing
Scheme
84.75 84.75 NIL NIL NIL Not started  Reason not known
Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.)
Name of the Agency :                   NRHM (Z.S.S)
Sl.
No. 
Name of the Work  Name of the
Block & District 
Specify Budget to be
spent under (Plan/Non-Plan/OHSP/NRHM
Project Cost
(In Lakh)
Total Allotment
received (In Lakh)
Expenditure (Amount in Lakh) Physical Progres 
Progress reported till
last review meeting 
Progress
during this month 
Cumulative
progress 
Not started
or in progress or completed 
If in progress,
please indicate the stage or if not started, reasons or if completed, handed over or not 
1 Construction of labour
room under IPHS Scheme
Jagatsinghpur
Jagatsinghpur 
NRHM 7.45 5.00 40% 15% 55% In Progress Slab casting is to be done centering work in progress 
2 Renovation of Biridi PHC
under IPHS Scheme
Biridi
Jagatsinghpur 
NRHM 7.93 5.00 40% 25% 65% In Progress Slab casting of ward, indoor
& OT completed, finishing work in progress   
3 Renovation to Dasabatia
PHC (N)
Balikuda
Jagatsinghpur 
NRHM 4.97 5.00 70% 5% 75% In Progress Grading complete, wall tile &
floor tile completed, fixing of door & window in progress 
4 Renovation to Balithua
PHC (N)
Erasama
Jagatsinghpur 
NRHM 8.20 5.00 10% 10% 20% In Progress One new room constructed &
completed, grading of roof
slab completed, wall tile &
floor tile is in progress   
Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.)
Name of the Agency :                   O.B & C.C
Sl.
No. 
Name of the Work  Name of the
Block & District 
Specify Budget to be
spent under (Plan/Non-Plan/OHSP/NRHM
Project Cost
(In Lakh)
Total Allotment
received (In Lakh)
Expenditure (Amount in Lakh) Physical Progres 
Progress reported till
last review meeting 
Progress
during this month 
Cumulative
progress 
Not started
or in progress or completed 
If in progress,
please indicate the stage or if not started, reasons or if completed, handed over or not 
1 Upgradation of
CHC Raghunathpur 
Raghunathpur
Jagatsinghpur 
NRHM 25.53 25.53 Nil 10% 10% In Progress O.P.D. building removing plaster & grading concrete of
OPD building is in progress
2 Upgradation of
CHC Manijanga
Tirtol
Jagatsinghpur 
NRHM 24.02 24.02 10% 10% 20% In Progress Old OPD building, one room tile completed, removing old
plaster from outside & inside of wall done and rough plaster completed   
3 Upgradation of
CHC Kujanga
Kujanga
Jagatsinghpur 
NRHM 14.81 14.81 10% 10% 20% In Progress FW wings, roof dismental, new roof casted, finishing work in progress  
4 Upgradation of
UGPHC Erasama 
Erasama
Jagatsinghpur 
NRHM 30.47 30.47 20% 20% 40% In Progress Grading floor tile, wall tile of
ward & OPD building partially
completed 
5 Upgradation of
UGPHC Balikuda  
Balikuda
Jagatsinghpur 
NRHM 28.00 28.00 20% 10% 30% In Progress Floor tile, wall tile & door &
window of ward is completed
for OPD building is in progress 
6 Upgradation of
CHC Naugaon 
Naugaon
Jagatsinghpur 
NRHM 32.08 32.08 10% 10% 20% In Progress RNTCP & administrative
building wall tile, floor tile, door & window fixing is completed & not handedover 
Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.)
Name of the Agency :                   Rural works Division 
Sl.
No. 
Name of the Work  Name of the
Block & District 
Specify Budget to be
spent under (Plan/Non-Plan/OHSP/NRHM
Project Cost
(In Lakh)
Total Allotment
received (In Lakh)
Expenditure (Amount in Lakh) Physical Progres 
Progress reported till
last review meeting 
Progress
during this month 
Cumulative
progress 
Not started
or in progress or completed 
If in progress,
please indicate the stage or if not started, reasons or if completed, handed over or not 
1 Tarikunda Disp. (Renovation) Raghunathpur
Jagatsinghpur 
TFC 3.00 3.00 100% NIL 100% Completed  One extension of room constructed & completed but not handedover
2 Jaipur PHC (N) Raghunathpur
Jagatsinghpur 
TFC 4.00 4.00 20% NIL 20% Stopped since 6 months New building constructed upto
plinth level, further work not executed 
3 Upgradation of
CHC Manijanga
Tirtol
Jagatsinghpur 
NRHM 24.00 24.00 60% 10% 70% In progress New building slab casted for two Nos. D-Type Quarter, plastering work is in progress
4 Upgradation of
UGPHC Kujanga 
Kujanga
Jagatsinghpur 
NRHM 12.00 12.00 60% 10% 70% In progress New building slab casted for two Nos. D-Type Quarter, plastering work is in progress
5 Upgradation of
UGPHC Balikuda  
Balikuda
Jagatsinghpur 
NRHM 12.00 12.00 60% 10% 70% In progress New building slab casted for two Nos. D-Type Quarter, plastering work is in progress
6 Upgradation of
CHC Biridi
Biridi
Jagatsinghpur 
NRHM 10.00 10.00 60% 10% 70% In progress New building slab casted for two Nos. D-Type Quarter, plastering work is in progress
7 Govt. Hospital at
Mulugaon 
Balikuda
Jagatsinghpur 
NRHM 12.00 12.00 NIL NIL NIL - Estimate submitted to NRHM
for administrative approval
Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.)
Name of the Agency :                   R & B (P.W.B) 
Sl.
No. 
Name of the Work  Name of the
Block & District 
Specify Budget to be
spent under (Plan/Non-Plan/OHSP/NRHM
Project Cost
(In Lakh)
Total Allotment
received (In Lakh)
Expenditure (Amount in Lakh) Physical Progres 
Progress reported till
last review meeting 
Progress
during this month 
Cumulative
progress 
Not started
or in progress or completed 
If in progress,
please indicate the stage or if not started, reasons or if completed, handed over or not 
1 Upgradation of DHH Jagatsinghpur
Jagatsinghpur 
NRHM 20.00 20.00 100% NIL 100% Completed  New second floor building constructed & finishing work
completed &  handed over
2 Upgradation of DHH Jagatsinghpur
Jagatsinghpur 
NRHM 25.00 25.00 25% 10% 35% In progress  Pediatric & Medical ward, grading, grill fixing, floor & wall tile laying is completed, construction of postmertom building, development ompound wall & approach road is to be taken up   
3 Upgradation of DHH Jagatsinghpur
Jagatsinghpur 
NRHM 100.00 - - - - - Design & drawing for construction of new 3 storied building is finalised, tender under process, awaiting for release of funds