| Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.) | ||||||||||
| Name of the Agency : P.R. Deptt. | ||||||||||
| Sl. No. |
Name of the Work | Name of the Block & District |
Specify Budget to
be spent under (Plan/Non-Plan/OHSP/NRHM |
Project Cost (In Lakh) |
Total Allotment
received (In Lakh) |
Expenditure (Amount in Lakh) | Physical Progres | |||
| Progress reported
till last review meeting |
Progress during this month |
Cumulative progress |
Not started
or in progress or completed |
If
in progress, please indicate the stage or if not started, reasons or if completed, handed over or not |
||||||
| 1 | Infrastructure
Development of CHC Raghunathpur |
Raghunathpur Jagatsinghpur |
Non plan grant | 5.33 | 5.33 | 70% | NIL | 70% | stopped since 8 months | Not
completed, new building constructed upto slab casting, finishing work not started |
| 2 | Infrastructure Development of CHC Tirtol |
Tirtol Jagatsinghpur |
Non plan grant | 5.33 | 5.33 | 70% | 5% | 75% | In progress | New building slab casting completed, Door & window fittings in progress |
| 3 | Infrastructure
Development of Erasama UGPHC |
Erasama Jagatsinghpur |
Non plan grant | 5.33 | 5.33 | 100% | -- | 100% | completed | Finishing work not taken up since six months due to shortage of funds & not handed over |
| 4 | Improvement & Renovation of Tarikunda PHC (N) |
Raghunathpur Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 100% | -- | 100% | completed | New building constructed & not handed over |
| 5 | Improvement & Renovation of Jaipur PHC (N) |
Raghunathpur Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | NIL | NIL | NIL | Not started |
-- |
| 6 | Renovation to Krushnanandapur PHC (N) |
Tirtol Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 50% | NIL | 50% | stopped since 8 months |
New building construction completed upto roof level |
| 7 | Jagannathpur PHC (N) | Tirtol Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 70% | NIL | 70% | stopped since 6 months |
New building constructed, slab casting done finishing work not started |
| 8 | Gorada PHC (N) | Kujanga Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 70% | NIL | 70% | In progress | Extension
of room constructed, slab casting completed, finishing work in progress |
| 9 | Rahama PHC (N) | Kujanga Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 50% | NIL | 50% | stopped since 8 months |
Extension
of room constructed, slab casting completed, finishing work not taken up |
| 10 | Potanai PHC (N) | Kujanga Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 100% | -- | 100% | completed | New structure constructed, completed & handed over |
| 11 | Potanai PHC (N)
Compound wall |
Kujanga Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 0 | 0 | 0 | Not started | Estimate nor prepared & submitted for countersign. |
| Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.) | ||||||||||
| Name of the Agency : P.R. Deptt. | ||||||||||
| Sl. No. |
Name of the Work | Name of the Block & District |
Specify Budget to
be spent under (Plan/Non-Plan/OHSP/NRHM |
Project Cost (In Lakh) |
Total Allotment
received (In Lakh) |
Expenditure (Amount in Lakh) | Physical Progres | |||
| Progress reported
till last review meeting |
Progress during this month |
Cumulative progress |
Not started
or in progress or completed |
If
in progress, please indicate the stage or if not started, reasons or if completed, handed over or not |
||||||
| 12 | Malahunka PHC (N) | Kujanga Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 100% | NIL | 100% | Completed | Construction of compound wall completed & handed over |
| 13 | Renovation to Balichua PHC (N) |
Erasama Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 100% | NIL | 100% | Completed | One extension room constructed, completed & handedover |
| 14 | Panchapali PHC (N) | Erasama Jagatsinghpur |
Non plan grant | 5.00 | 5.00 | 100% | NIL | 100% | Completed | Renovation work, tile, door & window fixing,plastring,colouring, painting & handed over |
| 15 | Dihasahi PHC (N) | Erasama Jagatsinghpur |
Non plan grant | 4.00 | 4.00 | 100% | NIL | 100% | Completed | Renovation work, tile, door & window fixing,plastring,colouring, painting & handed over |
| 16 | Malipur PHC (N) | Erasama Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | Not started | -- | NIL | Not started |
Not started |
| 17 | Piteipur PHC (N) | Jagatsinghpur Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 100% | NIL | 100% | Completed | Renovation work, tile, door & window fixing,plastring,colouring, painting & handed over |
| 18 | Kaduapada PHC (N) | Jagatsinghpur Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 100% | NIL | 100% | Completed | One extension room constructed, completed & handedover |
| 19 | Adhanga PHC (N) | Biridi Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 100% | NIL | 100% | Completed | One
room constructed, completed & handedover |
| 20 | Bagalpur PHC (N) | Biridi Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 60% | NIL | 60% | stopped since 8 months |
Renovation work such as grading, plastering, colouring completed partial compound wall executed |
| 21 | Borikina PHC (N) | Balikuda Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 80% | NIL | 80% | Stoped since 2 months |
Extension of one room constructed, some finishing work is pending |
| 22 | Osakana PHC (N) | Balikuda Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 60% | NIL | 60% | Stoped since 6 months |
Constructed
one new building, slab casting completed, finishing work is pending |
| Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.) | ||||||||||
| Name of the Agency : P.R. Deptt. | ||||||||||
| Sl. No. |
Name of the Work | Name of the Block & District |
Specify Budget to
be spent under (Plan/Non-Plan/OHSP/NRHM |
Project Cost (In Lakh) |
Total Allotment
received (In Lakh) |
Expenditure (Amount in Lakh) | Physical Progres | |||
| Progress reported
till last review meeting |
Progress during this month |
Cumulative progress |
Not started
or in progress or completed |
If
in progress, please indicate the stage or if not started, reasons or if completed, handed over or not |
||||||
| 23 | Dasabatia PHC (N) | Balikuda Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 60% | NIL | 60% | Work stopped since 6 months |
Constructed
one new building, slab casting completed, finishing work is pending |
| 24 | Machhagaon PHC (N) | Balikuda Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | NIL | NIL | NIL | Work not started |
Reason not known |
| 25 | Osakana PHC (N) | Balikuda Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | NIL | NIL | NIL | Work not started |
Reason not known |
| 26 | Alanahat PHC (N) | Naugaon Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 90% | NIL | 90% | Work stopped since 6 months |
One
new building constructed, finishing work completed site development pending |
| 27 | Deriki PHC (N) | Naugaon Jagatsinghpur |
Non plan grant | 3.00 | 3.00 | 90% | NIL | 90% | Work stopped since 6 months |
One
new building constructed, finishing work completed site development pending |
| 28 | Construction of Sub-Centre building at Gobardhanpur |
Kujanga Jagatsinghpur |
RCH - II (ZSS) | 5.50 | 5.50 | NIL | NIL | NIL | Not started |
Reason not known |
| 29 | Kanaguli Sub-Centre | Erasama Jagatsinghpur |
RCH - II (ZSS) | 5.50 | 5.50 | 100% | NIL | 100% | Completed | New
building constructed Not handedover |
| 30 | Olara Sub-Centre | Erasama Jagatsinghpur |
RCH - II (ZSS) | 5.50 | 5.50 | 100% | NIL | 100% | Completed | New
building constructed & handedover |
| 31 | Mundalo Sub-Centre | Jagatsinghpur Jagatsinghpur |
RCH - II (ZSS) | 6.10 | 6.10 | 100% | NIL | 100% | Completed | New
building constructed Not handedover |
| 32 | Repair of Sub-Centre building 24 Nos. |
8 Blocks Jagatsinghpur |
TFC | 24.00 | 24.00 | 90% | -- | 90% | 20 Nos. renovation completed | 20 Nos. renovation work completed & handedover handedover, 2 Nos. not takenup & 2 Nos. in progress |
| 33 | Construction of building under cluster housing scheme |
Manijanga, Kujanga, Balikuda Jagatsinghpur |
Cluster Housing Scheme |
84.75 | 84.75 | NIL | NIL | NIL | Not started | Reason not known |
| Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.) | ||||||||||
| Name of the Agency : NRHM (Z.S.S) | ||||||||||
| Sl. No. |
Name of the Work | Name of the Block & District |
Specify Budget to
be spent under (Plan/Non-Plan/OHSP/NRHM |
Project Cost (In Lakh) |
Total Allotment
received (In Lakh) |
Expenditure (Amount in Lakh) | Physical Progres | |||
| Progress reported
till last review meeting |
Progress during this month |
Cumulative progress |
Not started
or in progress or completed |
If
in progress, please indicate the stage or if not started, reasons or if completed, handed over or not |
||||||
| 1 | Construction of labour room under IPHS Scheme |
Jagatsinghpur Jagatsinghpur |
NRHM | 7.45 | 5.00 | 40% | 15% | 55% | In Progress | Slab casting is to be done centering work in progress |
| 2 | Renovation of Biridi PHC under IPHS Scheme |
Biridi Jagatsinghpur |
NRHM | 7.93 | 5.00 | 40% | 25% | 65% | In Progress | Slab
casting of ward, indoor & OT completed, finishing work in progress |
| 3 | Renovation to Dasabatia PHC (N) |
Balikuda Jagatsinghpur |
NRHM | 4.97 | 5.00 | 70% | 5% | 75% | In Progress | Grading complete, wall tile & floor tile completed, fixing of door & window in progress |
| 4 | Renovation to Balithua PHC (N) |
Erasama Jagatsinghpur |
NRHM | 8.20 | 5.00 | 10% | 10% | 20% | In Progress | One
new room constructed & completed, grading of roof slab completed, wall tile & floor tile is in progress |
| Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.) | ||||||||||
| Name of the Agency : O.B & C.C | ||||||||||
| Sl. No. |
Name of the Work | Name of the Block & District |
Specify Budget to
be spent under (Plan/Non-Plan/OHSP/NRHM |
Project Cost (In Lakh) |
Total Allotment
received (In Lakh) |
Expenditure (Amount in Lakh) | Physical Progres | |||
| Progress reported
till last review meeting |
Progress during this month |
Cumulative progress |
Not started
or in progress or completed |
If
in progress, please indicate the stage or if not started, reasons or if completed, handed over or not |
||||||
| 1 | Upgradation of
CHC Raghunathpur |
Raghunathpur Jagatsinghpur |
NRHM | 25.53 | 25.53 | Nil | 10% | 10% | In Progress | O.P.D. building removing plaster & grading concrete of
OPD building is in progress |
| 2 | Upgradation of CHC Manijanga |
Tirtol Jagatsinghpur |
NRHM | 24.02 | 24.02 | 10% | 10% | 20% | In Progress | Old
OPD building, one room tile completed, removing old plaster from outside & inside of wall done and rough plaster completed |
| 3 | Upgradation of CHC Kujanga |
Kujanga Jagatsinghpur |
NRHM | 14.81 | 14.81 | 10% | 10% | 20% | In Progress | FW wings, roof dismental, new roof casted, finishing work in progress |
| 4 | Upgradation of UGPHC Erasama |
Erasama Jagatsinghpur |
NRHM | 30.47 | 30.47 | 20% | 20% | 40% | In Progress | Grading
floor tile, wall tile of ward & OPD building partially completed |
| 5 | Upgradation of
UGPHC Balikuda |
Balikuda Jagatsinghpur |
NRHM | 28.00 | 28.00 | 20% | 10% | 30% | In Progress | Floor tile, wall tile & door & window of ward is completed for OPD building is in progress |
| 6 | Upgradation of CHC Naugaon |
Naugaon Jagatsinghpur |
NRHM | 32.08 | 32.08 | 10% | 10% | 20% | In Progress | RNTCP
& administrative building wall tile, floor tile, door & window fixing is completed & not handedover |
| Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.) | ||||||||||
| Name of the Agency : Rural works Division | ||||||||||
| Sl. No. |
Name of the Work | Name of the Block & District |
Specify Budget to
be spent under (Plan/Non-Plan/OHSP/NRHM |
Project Cost (In Lakh) |
Total Allotment
received (In Lakh) |
Expenditure (Amount in Lakh) | Physical Progres | |||
| Progress reported
till last review meeting |
Progress during this month |
Cumulative progress |
Not started
or in progress or completed |
If
in progress, please indicate the stage or if not started, reasons or if completed, handed over or not |
||||||
| 1 | Tarikunda Disp. (Renovation) | Raghunathpur Jagatsinghpur |
TFC | 3.00 | 3.00 | 100% | NIL | 100% | Completed | One extension of room constructed & completed but not handedover |
| 2 | Jaipur PHC (N) | Raghunathpur Jagatsinghpur |
TFC | 4.00 | 4.00 | 20% | NIL | 20% | Stopped since 6 months | New
building constructed upto plinth level, further work not executed |
| 3 | Upgradation of CHC Manijanga |
Tirtol Jagatsinghpur |
NRHM | 24.00 | 24.00 | 60% | 10% | 70% | In progress | New building slab casted for two Nos. D-Type Quarter, plastering work is in progress |
| 4 | Upgradation of UGPHC Kujanga |
Kujanga Jagatsinghpur |
NRHM | 12.00 | 12.00 | 60% | 10% | 70% | In progress | New building slab casted for two Nos. D-Type Quarter, plastering work is in progress |
| 5 | Upgradation of
UGPHC Balikuda |
Balikuda Jagatsinghpur |
NRHM | 12.00 | 12.00 | 60% | 10% | 70% | In progress | New building slab casted for two Nos. D-Type Quarter, plastering work is in progress |
| 6 | Upgradation of CHC Biridi |
Biridi Jagatsinghpur |
NRHM | 10.00 | 10.00 | 60% | 10% | 70% | In progress | New building slab casted for two Nos. D-Type Quarter, plastering work is in progress |
| 7 | Govt. Hospital at
Mulugaon |
Balikuda Jagatsinghpur |
NRHM | 12.00 | 12.00 | NIL | NIL | NIL | - | Estimate submitted to NRHM for administrative approval |
| Financial & Physical Progress Format of Civil Construction (Health & FW Deptt.) | ||||||||||
| Name of the Agency : R & B (P.W.B) | ||||||||||
| Sl. No. |
Name of the Work | Name of the Block & District |
Specify Budget to
be spent under (Plan/Non-Plan/OHSP/NRHM |
Project Cost (In Lakh) |
Total Allotment
received (In Lakh) |
Expenditure (Amount in Lakh) | Physical Progres | |||
| Progress reported
till last review meeting |
Progress during this month |
Cumulative progress |
Not started
or in progress or completed |
If
in progress, please indicate the stage or if not started, reasons or if completed, handed over or not |
||||||
| 1 | Upgradation of DHH | Jagatsinghpur Jagatsinghpur |
NRHM | 20.00 | 20.00 | 100% | NIL | 100% | Completed | New second floor building constructed & finishing work
completed & handed over |
| 2 | Upgradation of DHH | Jagatsinghpur Jagatsinghpur |
NRHM | 25.00 | 25.00 | 25% | 10% | 35% | In progress | Pediatric & Medical ward, grading, grill fixing, floor & wall tile laying is completed, construction of postmertom building, development ompound wall & approach road is to be taken up |
| 3 | Upgradation of DHH | Jagatsinghpur Jagatsinghpur |
NRHM | 100.00 | - | - | - | - | - | Design & drawing for construction of new 3 storied building is finalised, tender under process, awaiting for release of funds |